 Downtown Streetscape Improvements

Devon Excess Flow Force Main & Lift Station 

Bittersweet Water Reclamation Facility

Country Creek Streambank Stabilization 

North Avenue Resurfacing Project

On 6/11/2025, the Illinois Department of Transportation (IDOT) awarded Everlast Blacktop the construction contract for the resurfacing of North Ave between Oak Avenue and Lake Street. This segment of North Avenue qualifies for federal funding through the Surface Transportation Program. The work includes pavement resurfacing, spot concrete removal and replacement, ADA compliant crosswalks, landscape restoration and pavement marking. A highlight of the project will be a new on-street, striped bike lane along the south side of North Avenue between Eastern Ave and Prospect. 

8/15/2025

  • Paving along North Ave is expected to be complete on 8/15/25. 
  • Final landscaping and pavement markings are tentatively scheduled for the weeks of 8/18 and 8/25, respectively. Please use caution while traveling through the work zone during these operations.    

8/5/2025

  • Concrete work is complete on both the north and south sides of North Ave. The week of 8/4/2025, wood forms will be removed and all holes adjacent to the new walk will be backfilled.
  • The entire roadway has been milled and pavement patching/structure adjustment work also has begun. 
  • Paving operations are expected to start during the week of 8/11/2025.  
  • Everlast Blacktop has formally filed for an extension with IDOT and that request is currently being processed. The Village anticipates this extension to be granted. 

    IMPORTANT NOTE REGARDING THE 1ST DAY OF SCHOOL

  • Prior to Monday, 8/11/2025, all the new concrete corners will be open and the adjacent gaps will be backfilled to ensure safe walking paths to school. 
  • The median separating North Ave with the Bartlett Elementary bus lane is complete and this week's pavement patching will allow for safe bus access and student drop-off/pickup.  
  • Construction activities, including asphalt paving, will take place while school is in session. The contractor is aware of the new school schedule and will avoid the high traffic areas during the morning and afternoon rush periods.

7/18/2025

  • Concrete removal and replacement work began Monday, 7/14/2025. The intent is to complete all concrete work on the south side before moving to the north side. 
  • Median work in front of Bartlett Elementary is also underway to ensure intrusive work around the school is minimal once school starts. 
  • Contract completion (weather dependent) is August 1, 2025. However, due to a delay in the contract award, this date is subject to change upon IDOT approval. 

2025 Various Streets Resurfacing Project

8/15/2025:

  • Final paving began on Thursday, 8/14/25 in the neighborhoods north of Hawk Hollow Middle School. Paving will continue into the week of 8/18/25 and will continue moving from south to north. 
  • Work is being allowed on Saturday, 8/16/25. The Contractor will be working along Fairfax Ln and in the Harmony Grove/Bartlett Reserve subdivisions.
  • Once paving is complete, pavement marking and pavement preservation operations will be scheduled. 
  • Areas that were landscaped earlier this summer will be inspected prior to project completion, and any area found to be unsatisfactory will be replanted. 

8/5/2025:

  • Weather dependent, paving will resume Wednesday, 8/13/2025 and is expected to last 3-4 days. Bike path work on Struckman Blvd. is the last major work item needed prior to paving.
  • Final pavement markings and a pavement preservation application will be scheduled after paving is complete.

7/18/2025:

  • Earlier in the week of 7/14/2025, the contractor began placing the first lift of asphalt, starting from the south to north. This first lift is anticipated to be complete by early in the week of 7/21/2025. 
  • There will be a period of time before the final asphalt surface is placed to allow for structure adjustments in the roadway and punch-list concrete work. 
  • Please use caution and travel slowly through the work zone during paving operations.

6/26/2025:

  • Curb line structure adjustments are planned to be completed by the end of this week and the remaining curb will be poured on Saturday/Monday.
  • Oro Stone Landscaping continues placing topsoil and erosion control blanket. This work will continue over the next couple of weeks. 
  • Milling of the existing pavement is scheduled to begin Monday, 7/7/25. Please use caution when traveling through the work 

6/20/2025: 

  • Schroeder and Schroeder is 95% complete with their concrete work. They will be in town over the next few working days stripping forms, cleaning up, and filling the gap between the curb and pavement. 
  • Schroeder Asphalt is scheduled to begin asphalt driveway patches on  6/21/25. If your driveway is marked to receive a patch, it will be removed and replaced the same day and can be driven over immediately. 
  • Oro Stone Landscaping has also begun placing topsoil and erosion control blanket. This work will continue over the next couple of weeks. 

6/12/2025: 

  • Schroeder and Schroeder have completed concrete work along one side of the street on all streets included in the project. They will begin removing the opposite side the afternoon of 6/12/25. 
  • If sidewalk or curb is being removed through your driveway, door hangers will be passed out in advance letting residents know the tentative timeline for replacement. During those times when driveway access is prohibited, ON-STREET OVERNIGHT PARKING WILL BE ALLOWED. 
  • In an effort to complete all concrete work by the Fourth of July holiday weekend, Saturday work will be allowed during the month of June. 

6/5/2025:

  • Schroeder and Schroeder began removing and replacing sidewalk and curb & gutter this week. They started at the western entrance into the Streets of Bartlett and are currently on Amherst Drive and in the Harmony Grove/Bartlett Reserve subdivisions.
  • If sidewalk or curb is being removed through your driveway, door hangers will be passed out in advance letting residents know the tentative timeline for replacement. During those times when driveway access is prohibited, ON-STREET OVERNIGHT PARKING WILL BE ALLOWED. 
  • In an effort to complete all concrete work by the Fourth of July holiday weekend, Saturday work will be allowed during the month of June. 

As part of Bartlett’s general maintenance program, public works engineers put out to bid a construction contract that includes road resurfacing and concrete repair in various areas around town. This year’s contract was awarded to Schroeder Asphalt Services, Inc. Construction will begin in June with a final completion date of October 1. The 2025 areas are listed below. If you live in one of these areas, watch for mailings or door hangers with more project information. You also can download the Bartlett Connect app for project updates. 

Country Creek Subdivision
Amherst Dr
Plymouth Ct
Irvington Ct
Camdon Cir
Hampton Cir

Bartlett Reserve & Harmony Grove Subdivisions
Pleasant Dr
Melody Dr
Struckman Blvd
Harmony Dr
Wisteria Ct

Fairfax Crossing & Hawk Hollow Subdivisions
Village Ln
Gatewood Ln
Winston Ln
Hawk Hallow Dr

Fairfax Lane (Schick to Army Trail)
Stockton Ct
Lenox Ct
Fairfax Cir E & W

Bartlett Plaza Drive (Streets of Bartlett entrance drive off Main St)

 

Annual General Maintenance Activities

Each year, the Village of Bartlett undertakes a series of general maintenance projects that help to improve and maintain the village owned right-of-way. These project locations are dynamic, and the public works department strives to address the areas of need while also taking a systematic approach to effectively move through town. These general maintenance projects include:

  • Concrete Replacement (by contractor) – addresses issues in sidewalk and curb in various locations throughout the village.
  • Sidewalk Cutting (by contractor)– addresses small displacements (1/2” to less than 2”) between squares of sidewalk that do not warrant removal and replacement.

           7/18/2025: Project is Complete

           6/26/2025: Hard Rock Concrete Cutters are currently in Country Place, north of Newport Lane. Upon finishing, they will continue on to Amherst Drive, Ridings East, Bravo Point, and Charter Oaks neighborhoods as budget allows. The tentative completion date for this project is 7/3/25.

          6/20/2025: Hard Rock Concrete Cutters have finished in the Fairfax Commons/Fairfax Crossing neighborhoods and are currently in Country Place, north of Newport Lane. Upon finishing, they will continue on to Amherst Drive, Ridings East, Bravo Point, and Charter Oaks neighborhoods

          6/5/2025  - Hard Rock Concrete Cutters began in the Harmony Grove and Bartlett Reserve neighborhoods on Thursday, 6/4. Upon finishing, they will continue into the Fairfax Commons and Fairfax Crossing neighborhoods.

  • Pavement Marking (by contractor) – addresses faded lane markings,  pedestrian crosswalks, and bicycle lanes/crossings.
  • Pavement Crack Sealing (by contractor) – fills cracks in asphalt pavement to help prevent further cracking from the freeze thaw cycle.

8/15/2025 - SKC Construction began crack sealing on Friday, 8/15/25. They will start in the Brewster Creek Business Park and move counterclockwise through town addressing various streets along the way. This is a moving operation and is fairly non-intrusive.  Please use caution while passing through the work zone. 

8/5/2025 - Public Works staff will be meeting with the contractor this week to schedule a start date. Crack sealing operations will take place in various locations throughout the Village and is expected to last no more than 2 weeks. 

  • Pavement Preservation (by contractor) – spraying rejuvenation/preservation products on asphalt pavements (both roadway and bike paths) to help prolong the life of the pavement.
  • Cycle Trimming of Parkway Trees – all year long, the streets division of public works trims parkway trees to address low hanging limbs and promote healthy growth.